Stud Threadlocking Blind Holes

Stud Threadlocking / Thread Sealing Application Method A-103

This method pertains to the application of SAF-T-LOK products for threadlocking and/or threadsealing blind holes. The procedure is to be used when assembling threaded metal parts, using SAF-T-LOK threadlockers or thread sealing products.

Application Method

PROCEDURE

  1. Solvent clean the parts of any contamination. Use primer if parts must go back in service promptly.

  2. Apply T70 stud threadlocking compound to the male threads. Apply to the threads of the blind hole where the assembled stud will rest.
     
  3. Assemble the stud to the required depth or torque.

  4. The assembled parts will be sealed within one hour. A full cure will occur within 24 hours (or 4 hours with Primer).
     
  5. After cure of the T70 stud application, continue the assembly by applying the T42 threadlocking compound to the male threads of the stud.
     
  6. Assemble the joints to the required torque. Do not over tighten.
     
  7. The assembled parts will be low pressure sealed within one hour. A full cure will occur within 24 hours (or 4 hours with Primer).

Application Methods for Threadlockers, Thread Sealants, Penetrating and Porosity Sealants.

Threadlocking Threadsealing Application Method
Test Method for Fasteners
Stud Threadlocking Application Method
Pre-assembled threaded joints Application Method
Sealing of Threaded joints Application Method
Porosity Sealing Application Method